Great Wall Machinery Under-construction Projects Introduction in July

Great Wall Machinery, as a leading enterprise of domestic industry in the field of general slag powder grinding production line, regardless of declining current market, still win many orders of largeslag powder production lines this year. Now Greatwall is still busy in business negotiation, production arrangement, quality control and proceed the orders. So what are the Great Wall Machinery’s construction projects? Let's enjoy it.
  Firstly Harbin slag powder EPC project with annual capacity of 350,000t
  Harbin project was started in January 2015, and was officially launched on April 25, 2015. Now it has now been installed with online debugging.
图片4.jpg
  Secondly, Mei Country slag powder production line EPC project with annual capacity of 300,000t
  Mei Country project was started in February, 2015, and was officially launched on April 25, 2015. It is at present installed well, and the dust collector’s installation is 70% completed.
图片5.jpg
  Thirdly, Foshan EPC production project with annual slag powder capacity of 600,000t.
  Foshan project has started on June 14, 2015, right now frame is almost completed, and the next step is on the way.
图片6.jpg
  Fourthly, Xianning superfine slag powder production line EPC project with annual capacity of 300,000t
  Xianning Project was launched on June 13, 2015, at present the blast furnace has been installed completely, and the welding bridge of vertical grinding machine is beening welded.
图片7.jpg
  Finally, Xuzhou steel slag powder production line - EPC project with annual capacity of 300,000t
  The Xuzhou Project contract was signed in February 2015, and was officially launched on March 24, 2015. Now it is currently online debugging.
图片8.jpg